Park Projects

CENTRAL DISTRICT

Capital Projects at the Fairgrounds - 2018

1. Parks Office/Eagles Nest Roof Re-Roof – Replace existing roof which has leaking and soft spots in numerous locations.
a. Budget - $25,000
b. Timeline
i. Engineering and design completion date – not applicable
ii. Major permits secured – by contractor
iii. Bids issued – December 2017 – no bids, re-worked and re-submitted February 6, 2018 – deadline March 1, 2018
iv. Contractor chosen and contract completed – April 1, 2018
v. Construction start – April 2, 2018
vi. Project Completion – May 2, 2018

2. Fairgrounds Communication Upgrade more information coming
a. Budget - $20,000
b. Timeline – 

 i. Engineering and design completion date
ii. Major permits secured
iii. Bids issued
iv. Contractor chosen and contract completed
v. Construction start
vi. Project Completion

3. Fairgrounds Maintenance Yard and Maintenance Work Room more information coming
a. Budget - $75,000
b. Timeline – 
 i. Engineering and design completion date -
ii. Major permits secured -
iii. Bids issued -
iv. Contractor chosen and contract completed -
v. Construction start -
vi. Project Completion - 
4. Lobe Field Press Box – Construct a 2 story press box on Lobe Field #1 to enhance the amenities on this field.
a. Budget - $100,000
b. Timeline –
i. Engineering and design completion date - completed
ii. Major permits secured - completed
iii. Bids issued - completed
iv. Contractor chosen and contract completed – completed – JA Wright
v. Construction start – December 2017
vi. Project Completion – March 2018
5. Lobe Field #1 PA system upgrade
a. Budget - $23,000
b. Timeline
i. Bid – completed
ii. Contract – completed
iii. Installation – March, 2018
iv. Completion – March, 2018
6. Lobe Field #1 Improvements – Phase 2 – Synthetic Turf
a. Budget – $1,953,000
b. Timeline
i. Secure Funding – May 2018
ii. RFQ for Engineering/Architect – May 2018
iii. Engineering and design completion date – December 2018
iv. Major permits secured – SDAP 2/2018, Construction March 2019
v. Bids issued – March 2019
vi. Contractor chosen and contract completed – May 2019
vii. Construction start – June 2019
viii. Project Completion – December 2019