Park Projects

 CENTRAL DISTRICT - CAPITAL PROJECTS - FAIRGROUNDS - 2018

 1. Parks Office/Eagles Nest Roof Re-Roof – Replace existing roof which has leaking and soft spots in numerous locations.

Eagle's Nest Community Room

Budget: $25,000   

Status: The bids were issued December 2017, re-worked and re-submitted February 6, 2018 and the deadline was March 1, 2018. The contractor has been chosen and the contract will be completed by April 1, 2018.
Next: The construction will start April 2, 2018 and the project will be completed by May 2, 2018.

  
2. Fairgrounds Communication Upgrade - Communications contractor CTS to remove obsolete communications wiring, and upgrade existing communications wiring so that the monitoring of the fire suppression systems is consistent and there are less communication errors.
Budget: $20,000
Status: Work to begin May 1, 2018.

3. Fairgrounds Maintenance Yard and Maintenance Work Room
Budget: $75,000
Status:  more information to come 

4. Lobe Field Press Box – Construct a 2 story press box on Lobe Field #1 to enhance the amenities on this field.
Budget: $100,000
Status: The contractor has been chosen and the contract has been competed. The work is to be done by J.A. Wright. The construction was started December 2017.
Next:  The project will be completed by March 2018.

5. Lobe Field #1 PA System Upgrade
Budget: $23,000
Status: Installation has began (March 2018) and is expected to be completed by the end of March 2018.

 
6. Lobe Field #1 Improvements – Phase 2 – Synthetic Turf
Budget: $1,953,000
Status: Funding to be secured by May 2018. The RFQ for the Engineering / Architect to be completed by May 2018. The Engineering and design to be complete by December 2018.
Bids will be issued March 2019 and the contractor will be chosen by May 2019. The construction is scheduled to begin June 2019 with the project to be completed by December 2019.
Next:  
 

 NORTH KITSAP - CAPITAL PROJECTS - 2018

 Check back for updates

 SOUTH KITSAP - CAPITAL PROJECTS - 2018

 Check back for updates